top of page

Procurement Management in PMP [Exam Notes]

  • Writer: Karthick Kumar Rajappan
    Karthick Kumar Rajappan
  • Feb 24
  • 2 min read

Key Points

Example

Purpose

Obtain goods/services from outside the org.

Façade curtain wall via fixed‑price design‑build contract.

Activities

Plan Procurement → Conduct Procurement → Control Procurement

RFP → bidder conferences → technical + commercial evaluation → contract award.

Contract Types

FP (FFP/FPIF), Cost‑Plus (CPFF/CPIF), T&M, BOOT, etc.

FPIF façade with SAR 200 k fee ceiling.

Artefacts

Procurement Mgmt Plan, SOW, Bid Docs, Agreements, Claims Log


What is a Procurement Contract?


A contract is a legally binding agreement between a buyer and a seller (vendor/contractor) that defines what will be delivered, when, how, and at what cost.


Types of Procurement Contracts


There are three main categories of procurement contracts, each with subtypes:


Fixed-Price Contracts (FP)

Buyer pays a fixed total price for a well-defined product or service.

Best Used When:

  • Scope is clear and well-defined

  • Buyer wants to shift risk to seller


Subtypes:

Type

Description

Example

Firm Fixed Price (FFP)

Price is fixed. Seller bears all cost risk.

SAR 1,000,000 for landscaping the hotel. No extra if material costs go up.

Fixed Price Incentive Fee (FPIF)

Fixed price + bonus for performance. Incentives tied to cost, time, or quality.

SAR 900,000 for façade installation + SAR 50,000 bonus if finished 10 days early.

Fixed Price with Economic Price Adjustment (FPEPA)

Fixed price with provisions for inflation or currency changes.

SAR 5,000,000 for imported steel with 5% price adjustment if USD-SAR fluctuates more than 3%.

Cost-Reimbursable Contracts (CR)

Buyer reimburses seller for allowable costs, plus a fee or profit.

Best Used When:

  • Scope is not clearly defined

  • High uncertainty or R&D-type work


Subtypes:

Type

Description

Example

Cost Plus Fixed Fee (CPFF)

Reimburse all costs + fixed fee

Actual costs + SAR 200,000 fee for feasibility study of solar heating system

Cost Plus Incentive Fee (CPIF)

Reimburse costs + incentive based on performance

Actual costs + 70/30 split savings if HVAC redesign reduces cost below target

Cost Plus Award Fee (CPAF)

Award fee based on buyer’s satisfaction (subjective)

Custom architectural design: buyer awards up to SAR 100,000 based on innovation and presentation quality

Time and Material Contracts (T&M)

A hybrid contract: buyer pays hourly/daily rates + cost of materials.

Best Used When:

  • Scope is not fully known

  • Task is short-term or requires flexibility


Example:

SAR 350/hour for electrical engineer + materials for data room cabling. Total duration = 4 weeks.


Comparison Summary

Type

Cost Certainty

Scope Clarity

Buyer Risk

Seller Risk

Hint

FFP

High

High

Low

High

Most predictable for buyer

FPIF

Medium

High

Medium

Medium

Shared risk (incentives)

FPEPA

Medium

High

Medium

Medium

Long-term, inflation risk

CPFF

Low

Low

High

Low

Risk of buyers: overruns

CPIF

Low

Low

Medium

Medium

Motivates performance

CPAF

Low

Low

High

Low

Buyer judges award

T&M

Medium

Low

Medium

Medium

Short jobs/consultants

Real-Life Examples (Construction Project Context)

Scenario

Best Contract Type

Why

Full hotel fit-out with detailed specs

Firm Fixed Price (FFP)

Scope is known and stable

Specialized kitchen redesign (unclear scope)

Cost Plus Fixed Fee (CPFF)

Hard to estimate effort

Hiring a BIM consultant for 1 month

T&M

Scope evolves; short term

Road construction with fuel price fluctuation

FPEPA

Economic conditions vary

High-rise glass façade with bonus for early finish

FPIF

Incentivize early delivery


Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
bottom of page