Stakeholder Management in PMP [Exam Notes]
- Karthick Kumar Rajappan

- Feb 24
- 1 min read

Key Points | Example | |
Purpose | Proactively manage expectations and influence. | Local residents concerned about night‑time concrete pours. |
Activities | Identify → Plan Engagement → Manage Engagement → Monitor Engagement | Stakeholder register prioritises “High Power / High Interest” municipality. |
Techniques | Salience, Power–Interest grid, Stakeholder Cube, Personas | |
Artefacts | Stakeholder Register, Engagement Plan, Issue Log |
Putting It All Together – Mini End‑to‑End Example
Scenario: Mid‑project, the client asks to add a rooftop restaurant.
Integration – Log CR, perform impact analysis, convene CCB.
Scope – Update scope statement & WBS (new “Rooftop Restaurant” package).
Schedule – Add tasks, recalc critical path, maybe crash steel work.
Cost – Revise cost baseline; update EAC via bottom‑up estimate.
Quality – Define new quality metrics (kitchen ventilation, acoustic levels).
Resources – Acquire specialist kitchen consultant.
Communications – Inform stakeholders; amend dashboard.
Risk – Add risk “late kitchen equipment delivery”; plan mitigation.
Procurement – Issue new RFP for kitchen fit‑out; evaluate bidders.
Stakeholder – Engage chef‑operator early to capture requirements.
If the CCB rejects the change, none of the baselines move and the restaurant waits for a future phase. That sequence embodies every Process‑domain task.