Stakeholder Management in PMP [Exam Notes]

  • Writer: Karthick Kumar Rajappan
    Karthick Kumar Rajappan
  • Feb 24
  • 1 min read

Key Points

Example

Purpose

Proactively manage expectations and influence.

Local residents concerned about night‑time concrete pours.

Activities

Identify → Plan Engagement → Manage Engagement → Monitor Engagement

Stakeholder register prioritises “High Power / High Interest” municipality.

Techniques

Salience, Power–Interest grid, Stakeholder Cube, Personas


Artefacts

Stakeholder Register, Engagement Plan, Issue Log


Putting It All Together – Mini End‑to‑End Example


Scenario: Mid‑project, the client asks to add a rooftop restaurant.


  1. Integration – Log CR, perform impact analysis, convene CCB.

  2. Scope – Update scope statement & WBS (new “Rooftop Restaurant” package).

  3. Schedule – Add tasks, recalc critical path, maybe crash steel work.

  4. Cost – Revise cost baseline; update EAC via bottom‑up estimate.

  5. Quality – Define new quality metrics (kitchen ventilation, acoustic levels).

  6. Resources – Acquire specialist kitchen consultant.

  7. Communications – Inform stakeholders; amend dashboard.

  8. Risk – Add risk “late kitchen equipment delivery”; plan mitigation.

  9. Procurement – Issue new RFP for kitchen fit‑out; evaluate bidders.

  10. Stakeholder – Engage chef‑operator early to capture requirements.


If the CCB rejects the change, none of the baselines move and the restaurant waits for a future phase. That sequence embodies every Process‑domain task.